Site Risk Assessment: Cork

DePuy Ireland UC · LM DePuy Ireland UC · DePuy Synthes EMEA
Period FY2026
Date 15 Oct 2026
Under Review
Risk score
58.6
Calculated
Medium
Concluded rating
-
Audit interval
24 months

Score breakdown and data provenance

#FactorSelected criterionPtsSourceEvidence / provenance
1Site Operations/TypeManufacturing with onsite sterilization5Manual-
2Product ClassificationHigh-risk (Class III)5QMSQMS extract 2026-10-15, Cork
3Site TenureEstablished site with stable operating history1Manual-
4External Inspection CommitmentsOne or more critical commitments ★5QMSQMS extract 2026-10-15, Cork
5Regulatory ActionsOpen regulatory actions are overdue ★5QMSQMS extract 2026-10-15, Cork
6Internal Audit Coverage/Modality (Past 3 Years)Onsite audit within 3 yrs1QMSQMS extract 2026-10-15, Cork
7Internal Audit HistoryMinor observations only, on track2QMSQMS extract 2026-10-15, Cork
8Complaints & Post-Market TrendsLow/favorable trend1QMSQMS extract 2026-10-15, Cork
9Nonconformances/Near MissesLow volume/no adverse trend1QMSQMS extract 2026-10-15, Cork
10CAPA System PerformanceTimely and effective closure1QMSQMS extract 2026-10-15, Cork
11Field ActionsCaused by site, ongoing and late ★5QMSQMS extract 2026-10-15, Cork
12Significant Changes/TurnoverMultiple/significant or high turnover5Manual-
13New Product IntroductionsLimited routine3Manual-
14Regulatory/Standards ChangesNo new applicability1Manual-
Total (14 applicable factors)4141 ÷ (14 × 5) × 100 = 58.6

Review triggers and risk reviews

External Inspection Commitments: One or more critical commitments → Review required (359861ac-718a-45f5-841b-e7924c65e56a)
20 Nov 2026, 08:25 · System · Pending review · Transferred from matching trigger rule.
Regulatory Actions: Open regulatory actions are overdue → Review required (b2c1a052-8f27-49bf-a1de-146b7ea7f445)
20 Nov 2026, 08:25 · System · Pending review · Transferred from matching trigger rule.
Field Actions: Caused by site, ongoing and late → Review required (b099b197-8018-424b-a91a-3f57ced82355)
20 Nov 2026, 08:25 · System · Pending review · Transferred from matching trigger rule.

Holistic site conclusion

Not concluded.

Signatures

Author
Lisa Brennan
Pending
Site RC Leader
Daniel Keane
Pending
Site QM Representative
Priya Nair
Pending
CONFIDENTIAL - FOR INTERNAL USE ONLY · Generated 20 Nov 2026, 11:48
CONFIDENTIAL - FOR INTERNAL USE ONLY